THE IMPACT OF MATERIAL MANAGEMENT PRACTICES ON PERFORMANCE OF BUILDING CONSTRUCTION SITES IN SELECTED TERTIARY INSTITUTIONS IN CROSS RIVER STATE, NIGERIA
Published 2025-06-09
Keywords
- Material Management,
- Building Construction,
- Tertiary Institutions,
- Project Delivery,
- Cross River State
How to Cite
Copyright (c) 2025 Academic Journal of Science, Engineering and Technology

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
Abstract
This work is titled the impact of material management practice on building construction sites in tertiary institutions in Cross River State. The aim of this study is to evaluate the impact of material management practices on building construction sites in selected tertiary institutions in Cross River State with a view to enhancing effective and efficient management of materials in building construction projects. The objectives are; to identify the causes of ineffective material management process to the construction project delivery; to evaluate the impact of material mismanagement in the building construction sites. The study adopted stratified random sampling techniques, 200 copies of questionnaire were given to respondents drawn from a population of 432. This study adopted survey research design using questionnaire as instrument for data collection and bill of quantities. The findings of the study reveal that the causes of ineffective material management process to the construction project delivery in tertiary institution in cross river state includes; incompetency of the project manager; design error; loss of fiancé; ineffective construction manager; poor planning; lack of pre and post investigation under design and improper supervision; varied labour equipment; lack of legal penalty to offenders and rush work. Finally, the study indicates that cost has a positive effect with construction delivery in tertiary institutions in Cross River state. Time has a positive relationship with construction delivery in tertiary institutions in Cross River state. Quality has positive relationship with the construction delivery in tertiary institutions in Cross River state. This implies that a unit increase in cost, time and quality will lead to increase in construction delivery in tertiary institutions in Cross River state. The study recommends that each management techniques has its own peculiarity in term of the pretender and post tender activities and processes, division of risks between client and contractors, and the effectiveness of project monitoring and control
References
- Abdelhamid, T. S., and J. G. Everett. 2002. Physical demands of construction work: A source of workflow unreliability. Paper read at The 10th Conference of the International Group for Lean Construction (IGLC-10), August 6-8 2002, at Gramado, Brazil.
- Abdul-Rahman, H., M.A. Berawi, A.R. Berawi, O. Mohamed, M. Othman, and I. A. Yahya.
- 2006. ‘Delay mitigation in the Malaysian construction industry’, Journal of Construction Engineering and Management-Asce, 132: 125-33.
- Akintoye, Akintola, George McIntosh, and Eamon Fitzgerald. 2000. A survey of supply chain collaboration and management in the UK construction industry. European
- Ala-Risku, T., and M. Kärkkäinen. 2004. Material delivery problems in construction projects: A possible solution. International Journal of Production Economics 104 (1):19-29.
- Albert, Shakaulu and Ibrahim. 2018.Imact of Material Management Practices in the Nigerian Building Construction Industry8(1);1789-1796
- Alkass, S., Aronian, A. and Moselhi, 0. (1993) Computer-aided Equipment Selection for Transporting and Placing Concrete'. Journal of Construction Engineering and Afanagcment, Vol. 119, Issue 3, pp. 445465.
- Alwi, S., Hampson, K., and Mohamed, S. (1999). Investigation on the relationship between rework and Site Supervision in High Building construction in Indonesia. The second international conference on construction process reengineering.
- Alwi, S., K. Hampson, and S. Mohamed. 2002. Factor Influencing Contractors’ Performance in Indonesia: A Study of Non Value-Adding Activities. Paper read at The International Conference on Advancement in Design, Construction,
- Anwar, Z. Sohail, M. Shazia N. Hashim. H & Muhammad, S. A (2015). Factors Affecting Material Procurement, Supply and Management in Building Projects of Pakistan: A Contractor’s Perspective.
- Arbulu, R., A. Koerckel, and F. Espana. 2005. Linking production-level workflow with materials supply. Paper read at IGLC -13, july 2005, at Sydney, Australia.
- Arbulu, R.J., and G.H. Ballard. 2004. Lean supply systems in construction. Paper read at The 12th Annual Conference of the International Group for Lean Construction (IGLC-12), at Copenhagen, Denmark.
- Ballard, G. 2000. The Last Planner System of production control, School of Civil Engineering, Faculty of Engineering, The University of Birmingham.
- Ballard, G., and G. Howell. 1994. Implementing lean construction: Improving downstream performance. In Proceedings of the second Annual Conference on Lean Construction at Catolica Universidad de Chile. Santiago, Chile.
- Ballard, Glenn, and Greg Howell. 1998. What kind of production is construction? Paper read at Sixth Annual Conference of the International Group for Lean Construction (IGLC-6), at Guarujá, Brazil.
- Bamidele, T. A.andAkinradewo, F. A. (2016). Assessment of materials management on building projects in Ondo State, Nigeria. Retrieved from www.worldscienti ficnews.com
- Bell, L. C. &Stukhart, G., (1986). Attributes of Material Management Systems. Journal of Construction Engineering and Management, 112(1), pp. 14-21.
- Conte, A. S. I. 2002. Lean construction: From theory to practice. Paper read at 10th annual conference of International Group of Lean Construction (IGLC-10), at Gramado, Brazil.
- Cooper, Martha C., and Lisa M. Ellram. 1993. Characteristics of Supply Chain Management and the Implications for Purchasing and Logistics Strategy.
- Cox, Andrew, and Paul Ireland. 2002. Managing construction supply chains: the common sense approach. Engineering, Construction and Architectural Management 9 (56):409 - 418.
- Dainty, A. R. & Brooke, R. J., (2004). Towards improved construction waste minimization: a need for improved supply chain integration?.Survey Structural, 22(1), pp. 20-29.
- Dey, P. K., (2001). Re-engineering materials management- a case study on an Indian refinery. Business Process Management Journal, Volume 7, pp. 394-408.
- Donyavi, S. & Flanagan, R., (2009). The Impact of Effective Material Management on Construction Site Performance for Small and Medium Sized Construction Enterprises.
- Nottingham, Association of Researchers in Construction Management, pp. 11-20.
- Emmanuel C.E (2017) The International Journal Of Engineering And Science (Ijes) || Volume || 6 || Issue || 4 || Pages || Pp 32-47 : Assessment Of Materials Waste In The Construction Industry: A View Of Construction Operatives, Tradesmen And Artisans In Nigeria.
- Ergen. E., Akinci, B. and Sacks, R. (2003) Formalization and Automation of Effective Tracking and Locating of Precast Components in a Storage Yard, Proc. 91h Europ lA Intemational Conference, EIA9. E-Activities and Intelligent Support in Design and the Built Enviroment, Europia, Istanbul, pp. 31-37.
- Jaselkis and El-Mislami (2003) Journal of Construction Engineering and Management
- Volume 129, Issue 5: https://doi.org/10.1061/(ASCE)0733-9364(2003)129:5(473)
- Jaselskis, EJ., Anderson, M. R., Mum, C. T., Rodriguez, Y. and Njos, S. (1995) Radio-Frequency identification Applications in Construction Industry. Journal of Construction Engineering and Management, Vol. 12 1, No. 2, pp. 189-196.
- Kamalaeaswari, M. B. &Vedhajanani, U. (2015) International Journal Of Engineering Research & Technology (Ijert) : Process Analysis Of Material Procurement In Commercial Buildings And Recommendation
- Kaming, Peter F., Paul O. Olomolaiye, Gary D Holt, and Frank C. Harris. 1997. Factors Influencing Construction Time and Cost Overruns on High-Rise Projects
- Kanimozhi, G and Latha, P (2014). Material Management in Construction Industry. Indian Journal of Applied research, Vol. 4, Issue 4, 6-9.
- Kocakülâh, Mehmet C., Jason F. Brown, and Joshua W. Thomson. 2008. Lean manufacturing principles and their application. Cost Management 22 (3):16-27.
- Kofi A. (2012) Minimizing Materials Wastage at the Construction Stage of a Project through the Implementation of Lean Construction
- Manteau, E. K., (2007). The development of an information management system for materials management in large construction companies operating in the Ghanian construction industry, Kumasi: Kwame Nkrumah University of Science and Technology.
- Nathan G, Chin L, &Ataur, R.(2010). Recycling of construction and demolition materials as part of the waste Minimization strategy.
- Narimah B.K (2008): Improving Materials Management on Construction Projects
- Obiegbu, M.E. (2012). Unique Roles of Professional Builders in the Society. Being a paper presented at the One day Seminar organized by the Rivers and Bayelsa States Chapter of the Nigerian Institute of Building held at Port-Harcourt, Nigeria on the 18th November.
- O'Brien, W. J. 1999. Construction Supply-Chain Management: A Vision for Advanced Coordination, Costing, and Control. Stanford, California: NSF Berkeley-Stanford Construction Research Workshop.
- Ocheoha, I.A and Moselhi, O. (2013). Impact of building information modeling on just-in-time material Delivery. Department of Building, Civil and Environmental Engineering, Concordia University 1455 De Maisonneuve Blvd. West Montreal, Canada.
- Odusami, O.J.Oladiran, S.A. (2012) Evaluation of Materials Wastage and Control in Some Selected Building Sites In Nigeria (Emirates Journal For Engineering Research, 17 (2), 53-65 (2012))
- Patil A.R, Smita V. Pataskar, S.V. (2013). Analyzing material management techniques on construction project. International Journal of Engineering and Innovative Technology (IJEIT) 3(4), 96-100.
- Shitaw T. (2021) Ethiop. J. Sci. & Technol. 1 4(1): 1-19: Material Waste Minimization Techniques in Building Construction Project.
- Thangjam S.E (2015) International Journal of Geology, Agriculture and Environmental Sciences Volume – 3: Management of Construction Waste Materials:
- Thomas, H.R., Horman, M.D., De Souza, U and Zaviski, I. (2002). Benchmarking of labor intensive construction activities: Lean construction and fundamental principles of workforce management. Rotterdam, Netherlands: International Council for Research and Innovation in Building and Construction
- Tsegay Gebrehiweta , HanbinLuo (2017) Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study, Creative Construction Conference 2017, CCC 2017, 19-22
- Ugochukwu, O. C. (2014). Evaluating the Impact of Construction Crafts’ Skills Acquisition and Critical Knowledge Development on Project Performance in Nigeria (Doctoral thesis). Retrieved from http://my.unizik.edu.ng/postgraduate/dload2.php?downloads=976
- Vrijhoef, R. &Koskela, L. (2003). The four roles of supply chain management in construction. European Journal of Purchasing & Supply Management.
- Wahab A. B and A. F. Lawal, “An evaluation of waste control measures in construction industry in Nigeria”, African Journal of Environmental Science and Technology, Vol. 5(3), pp. 246-254, March 2011
- Womack, J.P., Jones, D.T. and Roos, D. (1990) the machine that changed the world: Based on the Massachusetts Institute of Technology
- Zakeri, M., Olomolaiye, P., Holt, G. D. & Harris, F. C., (1996). A survey on constraints on Iranian construction operatives' productivity. Construction management and Economics, 14(5), pp. 417-426.
- Zeb, A., Malik, S., Nauman, S. Hanif, H. and Amin, M.O. (2015). Factors Affecting Material Procurement, Supply and Management in Building Projects of Pakistan: A Contractor’s Perspective. Proceedings of 2015 International Conference on Innovations in Civil and Structural Engineering (ICICSE'15). Istanbul (Turkey), pp. 170-175.
- Zimmer, Eric R. 2006. Improving Lean Supply Chain Management in the Construction
- Zimmer, Eric, Ossama Salem, Ashraf Genaidy, and Richard Shell. 2008. Case study: Lean supply chain management in the construction projects. Paper read at 16th Annual Conference of the Internal Group for Lean Construction (IGLC-16), at Manchester, United Kingdom